University of Virginia / Moser Linear Accelerator, Charlottesville, VA

R. E. Lee & Son was selected by the University of Virginia to provide both Pre-Construction and Construction services. Work was negotiated as part of the University of Virginia “Special Projects” contract to include interior demolition and renovations for the replacement of a Linear Accelerator. Scope of work included demolition, HVAC, cast-in-place concrete, lead shielding, machine foundation alterations, framing, drywall, doors & hardware, finishes.

Project Highlights

Project Team

Owner: University of Virginia Health Systems
Architect: HKS, Inc.
Contractor: R. E. Lee & Son, Inc. / Tremain Wheatley/Cliff Shifflett

Project Delivery System

Negotiated. Pre-Construction & Construction Services. Stipulated Sum.

Construction Schedule

Eighteen weeks construction duration.

Project Description

Interior renovations of existing radiation treatment facility.