R. E. Lee & Son, Inc. was the contractor for the construction of a new concrete, steel and masonry football stadium, restrooms, gathering / assembly place with associated sitework to replace the bleacher system. Work included structural and MEP tie-in to the existing Squash Building.

Project Highlights

Project Team

Owner: Woodberry Forest School / Bruce Tibbetts
Architect: Bartzen & Ball PLLC / Tut Bartzen
Contractor: R. E. Lee & Son, Inc. / John Barret

Project Delivery System

Cost plus Fee with Guaranteed Maximum Price

Construction Schedule

Proceeding under a phased development plan

Construction Type

Concrete, steel and masonry.